Revised Havant Thicket Reservoir pipeline plan submitted for approval
There is a new promise that the Havant Ticket Reservoir
pipeline will use the latest tunnelling technology to reduce
the impact on residents and neighbourhoods. Portsmouth Water
has submitted
a revised planning application to build the 5.3km of twin
pipeline which will draw out and fill Havant Thicket
Reservoir with spring water.
Plans show a dual pipeline between Bedhampton Springs
and Havant Thicket Reservoir using a combination of
traditional ‘open-cut’ and new microtunneling technology to
bore the tunnels.
Since the original permission was granted in 2021,
consultants Ward and Burke have devised a new route and will
use new microtunneling technology. Both will lessen the
impact of construction on local communities and minimise the
impact on the local environment, said Portsmouth Water.
This planning application, submitted to Havant Borough
Council, also seeks permission for a new plant at Bedhampton
Pumping Station, with changes to two Bedhampton operational
buildings and permanent diversion of footpath 34.
Outline planning for
an underground cross-connection chamber and above-ground
kiosk at the reservoir site with vehicular accesses for
maintenance is the second part of this planning application
reference APP/24/00405.
Microtunnelling is an automated, remotely controlled process
that bores a tunnel hole and then pushes the pipes through
it. Some 10,600m of pipeline will be installed using a
combination of open-cut and microtunnelling techniques.
There will be nine shafts sites that allow the tunnels to go
to different depths as required to lay the pipeline.
An example of microtunnelling on a previous project,
regarding Havant Thicket Reservoir
An example of microtunnelling on a previous project (LDRS)
Portsmouth Water said using microtunneling minimises road
and footpath closures and disruption. It will reduce the
amount of extracted waste materials from underground, soil
and rock that need to be removed and dealt with and it
allows the tunnels to go under rivers and rail lines.
Portsmouth Water has given two reasons to lay and use a dual
pipeline for this project, estimated to take three years.
First, by having two pipes it means maintenance work can be
carried out on one, while the other carries water.
The second reason is to allow Southern Water’s plans to pump
recycled, treated wastewater into the reservoir, if they are
approved.
A report in the planning documents from consultants Atkins
Realis said that £100m could be saved by Southern Water
customers if a pipeline allowing for the Southern Water
recycling project is laid at the same time.
The impact on the
environment and disruption to residents will again be
efficient as the work for the project is done once not
twice.
Southern Water said the plans will help future-proof the
south of England from drought. The controversial project
will be decided upon later this year.
The results of the public consultation on Hampshire water
transfer and water recycling project have just been
published and are available as a downloadable document.
Havant Borough Council planning chiefs will decide on
planning application reference
APP/24/00405 this month for work to start in April, said
Portsmouth Water.
Petersfield Post March 11th
Page updated:
Tuesday March 18, 2025